| Due to the very limited space in the Kirson
production halls it got more and more difficult during the past few years to decide where
to place a new piece of equipment or a new machine. Sometimes more time had to be spent on
the decision where to place a machine than on the decision how the machine should look
like. During a Kaizen project
(Continuous improvement process) in 2001 the workforce created a lot of improvement ideas.
Some of the best ideas could not be realized due to the limited space in the existing
buildings.
These two factors together with some
other ideas lead towards the end of 2001 to the decision to add 1.400 m² of space for the
production equipment. Besides offering more space this measure should also improve the
working conditions in the plant. Both the improvement of the air quality as well as the
handling of heavy goods and machine parts are at the top of the improvement agenda.

continue |
All jobs on time since the beginning Permission to build was granted very fast by
the local authorities. Therefore the work on the building could already start by the end
of March 2002. The building contractor, Zapf GmbH of Bayreuth, handed over the keys
punctually by the beginning of August. Precisely defined requirements and a very tight
control of all tasks by Zapf GmbH made sure that everything was completed on time and
Kirson is very satisfied with the quality of the building.
Removal and improvement of
five production lines
Every four weeks one of five
production lines will be moved from the older part of the plant into the new production
hall. Many improvements will be added to the machines by the Kirson engineering department
as well as the other suppliers involved. The first machine has already been relocated and
started production at the end of August.
Overtime of the Kirson workforce at
the weekends helps that the customers will not have to suffer delays or other consequences
due to the removal and improvement works on the production lines.
From today's point of view,
all works will be completed on time
Four of the five machines that shall
be relocated will already run in the new production hall in November. During the opening
celebration on Friday, November 15th, many customers and invited guests from the area will
have the possibility to convince themselves of the successful relocation. The fixed date
for the opening is both incentive and motivation for all the people involved at Kirson to
finish their work on time if nothing unforeseen should happen. |
During the Whitsun flood 1999 in Neustadt on the Danube
Kirson had almost been afflicted. Even though the plant is several kilometres away from
the river, the waters of the flood came to a stop only less than 100 metres in front of
the factory gates. If the level of the flood had risen for another 50 cm, Kirson would
also have been affected.
Several workers of Kirson were less fortunate at that
time. Three of them were very heavily afflicted. Their houses stood several metres under
water and had to be refurbished completely after the flood. Because our affected
colleagues experienced a great wave of solidarity from many different sides in 1999, the
Kirson management and works committee wanted to pay back some of this solidarity to the
victims of the flood disaster in Bavaria and Eastern Germany. |
Due to
the actual high demand for scrims and a lot of additional work caused by the building of
the new production hall, many employees and workers have worked a lot of overtime
recently. Therefore the proposal was made to donate not only money but also overtime. In
order to enhance the willingness to donate, the company promised to add a certain amount
on top of each given Euro.
The programme was spontaneously supported by
a large share of the workforce. Including the support of the company the amount of 10.000
Euro was gathered within a very brief period. In the meantime the money has already been
donated and the workforce hopes, that it will be made available to the victims of the
flood disaster within a short time. |